DT_BOM
Fill the PV3.1 equipment materials (BOM) table.
Fills the EQUIPMENT MATERIALS (bill of materials) table on the PV3.1 sheet from the project's permit BOM. If the sheet already has the standard table, it's filled in place; otherwise the command creates it at the standard spot with the standard formatting.
On the ribbon: JobEngine → Drawing Tools → BOM — the button appears only while PV3.1 is the active layout.
When to use it
After LOAD_DT, when you're working the PV3.1 sheet.
Prerequisites
Same as the wire schedule — LOAD_DT run on this drawing first, PV3.1 layout active.
Common problems
| Message | What to do |
|---|---|
Cannot fill the PV3.1 BOM yet. … No BOM cache on this drawing — run LOAD_DT first. | Run LOAD_DT, then re-run. If LOAD_DT noted the session has no permit BOM, complete the design wizard in JobEngine first, then re-run LOAD_DT. |
This drawing's cached BOM belongs to a different session — run LOAD_DT for the current session. | Run LOAD_DT and pick the right session. |